Touch Up Work

Now that the new concrete is in place we are working hard to smooth out the transition from path to turf and vice versa.  In some cases we were able to simply add soil and seed, but in others we had to do quite a bit of work.   Due to the timing and scope of some of the areas to be repaired, sod was a better option than seed.  In any case, we prepped for 8 pallets of sod (no more than 2-3 feet wide in any one place) last week.  The sod arrived late today and we placed about 5 pallets on the ground.  We will wrap up tomorrow and begin the process of taking care of it.  We'll do another 8 pallets next week once we get it prepped.  Some holes will be "cart path only" until the sod has a chance to root into the soil.  Holes 3, 6, and possibly 7 will be CPO starting this week.  When we get the back nine taken care of it's possible that another hole or two gets added to the list.  


Strip sod along path where grade didn't match concrete


Add soil 


Grade soil to meet path

New sod being installed