The big irrigation surprise is not the only excitement this holiday season. Just a pitching wedge away is the bridge on 10 which is currently under repair. This bridge was slated to be resurfaced, but once we started removing the old deck boards we found rotten joists and pilings. Replacing many joists, a few beams, and some of the pilings is required before completing the deck and rail boards on top. We are doing some unplanned earthwork to improve drainage beneath the bridge so that the new boards will have a chance. The extra lumber needed for beneath the deck has been ordered and will take a few days to arrive. This obviously adds some time to the process, but Ernie and Dalton along with help from our guys are doing an awesome job getting it back together as quickly as possible. For the time being we ask that you continue to play hole 10 as a par 3.
|
Rotten joists are being replaced |
|
Both ends are being rebuilt and drainage is being installed |
|
New deck is in place while we wait on additional lumber to be delivered |